PMI-ACP Question #286: Real Exam Question with Answer & Explanation
The correct answer is C: It is defined by the Scrum Master. The Definition of Done (DoD) is established by the Development Team (or the broader Scrum Team), not solely by the Scrum Master. The Scrum Master's role is to facilitate and coach, not to dictate quality criteria. The other statements are accurate: the DoD serves as exit criteria
Question
Which statement is least accurate when providing a definition of "Done"?
Options
- AIt is the exit criteria to determine whether a product backlog item is complete
- BIt may vary depending on the project
- CIt is defined by the Scrum Master
- DIt becomes more complete over time
Explanation
The Definition of Done (DoD) is established by the Development Team (or the broader Scrum Team), not solely by the Scrum Master. The Scrum Master's role is to facilitate and coach, not to dictate quality criteria. The other statements are accurate: the DoD serves as exit criteria for Product Backlog Items (A), it can vary across projects depending on context (B), and as the team matures and improves, the DoD typically becomes more rigorous and comprehensive over time (D).