PMI-ACP · Question #275
Which Agile methodology runs one week iterations; leverages the use of pair programming; and includes the roles of coach, customer, programmer, tracker, and tester?
The correct answer is D. XP. Extreme Programming (XP) is the correct answer. XP is characterized by short, typically one-week iterations, and pair programming (two developers sharing one workstation) is a core practice. Its defined roles include the Coach (guides the team), Customer (defines requirements…
Question
Which Agile methodology runs one week iterations; leverages the use of pair programming; and includes the roles of coach, customer, programmer, tracker, and tester?
Options
- ALean
- BAgile One
- CScrum
- DXP
How the community answered
(32 responses)- A3% (1)
- B3% (1)
- D94% (30)
Explanation
Extreme Programming (XP) is the correct answer. XP is characterized by short, typically one-week iterations, and pair programming (two developers sharing one workstation) is a core practice. Its defined roles include the Coach (guides the team), Customer (defines requirements and priorities), Programmer (writes code and tests), Tracker (monitors progress), and Tester (ensures quality). Scrum uses different roles (Scrum Master, Product Owner, Development Team) and longer sprints (1-4 weeks). Lean and 'Agile One' do not match this description.
Topics
Community Discussion
No community discussion yet for this question.