Which Agile methodology runs one week iterations; leverages the use of pair programming; and includes the roles of coach, customer, programmer, tracker, and tester?

The correct answer is D. XP. Extreme Programming (XP) is the correct answer. XP is characterized by short, typically one-week iterations, and pair programming (two developers sharing one workstation) is a core practice. Its defined roles include the Coach (guides the team), Customer (defines requirements…

Submitted by klara.se· Apr 18, 2026Team Performance

Question

Which Agile methodology runs one week iterations; leverages the use of pair programming; and includes the roles of coach, customer, programmer, tracker, and tester?

Options

  • ALean
  • BAgile One
  • CScrum
  • DXP

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    3% (1)
  • D
    94% (30)

Explanation

Extreme Programming (XP) is the correct answer. XP is characterized by short, typically one-week iterations, and pair programming (two developers sharing one workstation) is a core practice. Its defined roles include the Coach (guides the team), Customer (defines requirements and priorities), Programmer (writes code and tests), Tracker (monitors progress), and Tester (ensures quality). Scrum uses different roles (Scrum Master, Product Owner, Development Team) and longer sprints (1-4 weeks). Lean and 'Agile One' do not match this description.

Topics

#Extreme Programming (XP)#XP Roles#XP Practices#Agile Methodologies