Which should NOT take place at the daily Scrum?
The correct answer is A. The Product Owner gives an update. The daily Scrum (standup) is a 15-minute time-boxed event owned by and designed for the Development Team. Each team member answers three questions: What did I do yesterday? What will I do today? Are there any impediments? The Scrum Master facilitates and manages the time-box…
Question
Which should NOT take place at the daily Scrum?
Options
- AThe Product Owner gives an update
- BThe Scrum Mater manages the time-box
- CThe Development Team answers the three questions
- DIssues are raised and documented
How the community answered
(30 responses)- A93% (28)
- B3% (1)
- D3% (1)
Explanation
The daily Scrum (standup) is a 15-minute time-boxed event owned by and designed for the Development Team. Each team member answers three questions: What did I do yesterday? What will I do today? Are there any impediments? The Scrum Master facilitates and manages the time-box. Issues may be noted for follow-up. The Product Owner is not required to speak or give updates during this ceremony - their involvement would shift the focus away from the team's self-coordination.