Which should NOT take place at the daily Scrum?

The correct answer is A. The Product Owner gives an update. The daily Scrum (standup) is a 15-minute time-boxed event owned by and designed for the Development Team. Each team member answers three questions: What did I do yesterday? What will I do today? Are there any impediments? The Scrum Master facilitates and manages the time-box…

Submitted by dimitri_ru· Apr 18, 2026Team Performance

Question

Which should NOT take place at the daily Scrum?

Options

  • AThe Product Owner gives an update
  • BThe Scrum Mater manages the time-box
  • CThe Development Team answers the three questions
  • DIssues are raised and documented

How the community answered

(30 responses)
  • A
    93% (28)
  • B
    3% (1)
  • D
    3% (1)

Explanation

The daily Scrum (standup) is a 15-minute time-boxed event owned by and designed for the Development Team. Each team member answers three questions: What did I do yesterday? What will I do today? Are there any impediments? The Scrum Master facilitates and manages the time-box. Issues may be noted for follow-up. The Product Owner is not required to speak or give updates during this ceremony - their involvement would shift the focus away from the team's self-coordination.