PMI-ACP · Question #143
Who is responsible for the "definition of done"?
The correct answer is A. The team. The entire team - developers, testers, and the Product Owner together - owns and is responsible for the definition of done (DoD). The DoD is a shared agreement on what criteria must be met for a story or increment to be considered complete. It is not solely the Product Owner's (B
Question
Who is responsible for the "definition of done"?
Options
- AThe team
- BThe Product Owner
- CManagement
- DProject manager
How the community answered
(19 responses)- A89% (17)
- B5% (1)
- C5% (1)
Explanation
The entire team - developers, testers, and the Product Owner together - owns and is responsible for the definition of done (DoD). The DoD is a shared agreement on what criteria must be met for a story or increment to be considered complete. It is not solely the Product Owner's (B), management's (C), or project manager's (D) responsibility. Because the team executes the work, they must collectively agree on and uphold the standards that define completion.
Topics
Community Discussion
No community discussion yet for this question.