PMI-ACP · Question #109
PMI-ACP Question #109: Real Exam Question with Answer & Explanation
The correct answer is D: Raise the visibility of each person's work and to ensure the work is integrated.. The daily standup (Daily Scrum) is a short synchronization meeting for the development team. Its purpose is to surface what each person is working on, identify integration points and dependencies, and expose blockers — raising visibility across the team so work can be coordinat
Question
The best description of the purpose of the daily standup in Agile projects is to:
Options
- AResolve the key issues and risks that are likely to hinder project progress.
- BProvide insight and reassurance to the Product Owner to strengthen that relationship.
- CInform the project lead of project status for reporting to stakeholders.
- DRaise the visibility of each person's work and to ensure the work is integrated.
Explanation
The daily standup (Daily Scrum) is a short synchronization meeting for the development team. Its purpose is to surface what each person is working on, identify integration points and dependencies, and expose blockers — raising visibility across the team so work can be coordinated and integrated smoothly. It is NOT for resolving issues (those are taken offline), reassuring the Product Owner (A/B), or reporting status upward to stakeholders (C). It is a team-to-team coordination event. The three classic questions (what did I do, what will I do, any blockers) all serve the goal of work visibility and integration.