PL-900 · Question #138
PL-900 Question #138: Real Exam Question with Answer & Explanation
The correct answer is C: Approval flow. You should use approval flows to manage the approval process. These are used for managing approval processes or automating the approval system, like approving an inventory request or approving a leave request. You should not use schedule flows. Schedule flows are used when you wa
Question
Your company uses Dynamics 365. When a service ticket is created, a technician visit to the customer is required. Technician visits should be consented to by a manager. You need to ensure that the process is followed. What should you use?
Options
- AScheduled flow
- BBusiness rule
- CApproval flow
- DButton flow
Explanation
You should use approval flows to manage the approval process. These are used for managing approval processes or automating the approval system, like approving an inventory request or approving a leave request. You should not use schedule flows. Schedule flows are used when you want to perform an action on a specific time or duration, like after an hour or once a day. You should not use button flows. Button flows are used to automate tasks with a click of a button. Once a button is clicked, it will trigger an action. You should not use business rules. These are used when you want to perform a series of tasks in a specific order.
Topics
Community Discussion
No community discussion yet for this question.