PK0-005 · Question #598

PK0-005 Question #598: Real Exam Question with Answer & Explanation

The correct answer is B: Key performance indicators. Key performance indicators (KPIs) are measurable values that show whether project goals and objectives have been achieved. Tracking KPIs allows the project manager to identify if the project is meeting its intended outcomes.

Project Management Concepts

Question

Which of the following would help a project manager identify that project goals have been reached?

Options

  • AAudit report
  • BKey performance indicators
  • CBacklog
  • DLessons learned

Explanation

Key performance indicators (KPIs) are measurable values that show whether project goals and objectives have been achieved. Tracking KPIs allows the project manager to identify if the project is meeting its intended outcomes.

Topics

#Key Performance Indicators#Project Goals#Performance Measurement#Project Success