PK0-005 Question #407: Real Exam Question with Answer & Explanation

The correct answer is C: Project success criteria. Project success criteria define the specific goals and deliverables that must be completed by the end of the project, including meeting cost and time requirements. These criteria help guide the project team and stakeholders in understanding what constitutes success for the projec

Project Life Cycle Phases

Question

During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?

Options

  • AWork breakdown structure
  • BChange log
  • CProject success criteria
  • DMilestone chart

Explanation

Project success criteria define the specific goals and deliverables that must be completed by the end of the project, including meeting cost and time requirements. These criteria help guide the project team and stakeholders in understanding what constitutes success for the project, ensuring that the project stays focused on its objectives. The success criteria should be clearly defined during the initiation phase to set expectations and track progress throughout the project.

Topics

#Project initiation#Project success criteria#Project goals#Deliverables