The correct answer is D: Norming. {"question_number": 2, "explanation": "This describes the Norming stage of Tuckman's Team Development Model (Forming → Storming → Norming → Performing → Adjourning). In Norming, team members have resolved earlier conflicts, are building cohesion, becoming comfortable with each ot

Project Management Concepts

Question

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

Options

  • APerforming
  • BAdjourning
  • CForming
  • DNorming

Explanation

{"question_number": 2, "explanation": "This describes the Norming stage of Tuckman's Team Development Model (Forming → Storming → Norming → Performing → Adjourning). In Norming, team members have resolved earlier conflicts, are building cohesion, becoming comfortable with each other, and productivity is increasing. The key indicator here is 'comfortable asking for help' - this reflects growing trust and collaboration. Performing would describe a team already operating at peak efficiency. Forming is the initial meeting stage, and Adjourning is the dissolution phase at project close.", "generated_by": "claude-sonnet", "llm_judge_score": 5}

Topics

#Team development stages#Tuckman's stages#Norming stage#Project team management

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions