External resources are required for a program. The program manager receives bids from multiple vendors and presents the top vendor to the program governance board. One program governance board member
The correct answer is D. Initiate a new vendor selection bid process. When a governance board member attempts to influence vendor selection based on a personal relationship, the integrity of the procurement process is compromised. Adding the vendor to the approved list (A) rewards the inappropriate influence. Agreeing to engage the vendor (C) direc
Question
External resources are required for a program. The program manager receives bids from multiple vendors and presents the top vendor to the program governance board. One program governance board member asks the program manager to select a vendor that was dismissed early in the selection process because they were not on the approved vendor list. The program manager learns that this program governance board member has a personal connection to this vendor. What should the program manager do?
Options
- AAdd the vendor to the approved list
- BReport an ethics violation
- CAgree to engage the vendor due to the program governance board member's program influence
- DInitiate a new vendor selection bid process
How the community answered
(32 responses)- A16% (5)
- B34% (11)
- C9% (3)
- D41% (13)
Explanation
When a governance board member attempts to influence vendor selection based on a personal relationship, the integrity of the procurement process is compromised. Adding the vendor to the approved list (A) rewards the inappropriate influence. Agreeing to engage the vendor (C) directly violates procurement integrity. Reporting an ethics violation (B) may ultimately be warranted, but the immediate corrective action is to neutralize the tainted process. Option D is correct because initiating a new vendor selection bid process resets the evaluation on objective, merit-based criteria, removes the tainted outcome, and protects the program from a governance-compromised procurement decision-while the conflict of interest should also be documented and escalated through proper channels.