PGMP · Question #314
You are the program manager for your organization and are reviewing several proposed change requests for your program. Mary, a stakeholder, who has made a change request is asking why it is taking…
The correct answer is D. It is the review of the impact of the change on the program's knowledge areas. Integrated Change Control is a comprehensive process that evaluates the impact of proposed changes across all project or program knowledge areas, not just the triple constraints.
Question
You are the program manager for your organization and are reviewing several proposed change requests for your program. Mary, a stakeholder, who has made a change request is asking why it is taking you so long to review the change. You tell her that you must perform integrated change control to review each change request. What is integrated change control?
Options
- AIt is the review of the impact of the change on the program's triple constraints.
- BIt is the review of the impact of the change on the time, cost, scope, and quality baselines.
- CIt is the review of the impact of the change on the program's Iron Triangle.
- DIt is the review of the impact of the change on the program's knowledge areas.
How the community answered
(46 responses)- A2% (1)
- B4% (2)
- D93% (43)
Why each option
Integrated Change Control is a comprehensive process that evaluates the impact of proposed changes across all project or program knowledge areas, not just the triple constraints.
Reviewing only the triple constraints (time, cost, scope) is incomplete; integrated change control spans all knowledge areas, not just those three.
Reviewing time, cost, scope, and quality baselines is still incomplete because integrated change control must evaluate impacts on all knowledge areas including risk, HR, procurement, and communications.
The Iron Triangle refers to the same three constraints as option A and is similarly an incomplete description of integrated change control.
Integrated Change Control requires assessing a change request's impact across all knowledge areas - scope, schedule, cost, quality, resources, communications, risk, procurement, and stakeholders - to understand the full ripple effect of any modification. Limiting the review to only time, cost, and scope (the triple constraints or Iron Triangle) would miss critical impacts in other areas, making a fully integrated assessment necessary.
Concept tested: Integrated Change Control scope across all knowledge areas
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.