nerdexam
PMIPMI

PGMP · Question #285

PGMP Question #285: Real Exam Question with Answer & Explanation

Sign in or unlock PGMP to reveal the answer and full explanation for question #285. The question stem and answer options stay visible for context.

Procurement Management

Question

Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

Options

  • AIt depends on what the outcome of a lawsuit will determine.
  • BNo, the ZAS Corporation did not complete all of the work.
  • CIt depends on what the termination clause of the contract stipulates.
  • DYes, the ZAS Corporation did not choose to terminate the contract work.

Unlock PGMP to see the answer

You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Contract Management#Procurement Management#Termination Clause#Contractual Liability
Full PGMP PracticeBrowse All PGMP Questions