PGMP · Question #192
You are the program manager for your organization. Management has assigned you to a new program that has been chartered. Your team is in the process of the Manage Program Issues process. One of the…
The correct answer is D. Program issues register updates. This question tests knowledge of the two outputs produced by the Manage Program Issues process.
Question
You are the program manager for your organization. Management has assigned you to a new program that has been chartered. Your team is in the process of the Manage Program Issues process. One of the two outputs of this process is change requests. Which one of the following is the other one?
Options
- AAudit reports
- BProgram management plan
- CProgram performance reports
- DProgram issues register updates
How the community answered
(53 responses)- A2% (1)
- B2% (1)
- C6% (3)
- D91% (48)
Why each option
This question tests knowledge of the two outputs produced by the Manage Program Issues process.
Audit reports are produced by quality audit processes, not by the Manage Program Issues process.
The program management plan is an input to issue management, not an output - it provides the framework within which issues are managed.
Program performance reports are produced during performance reporting processes and are not a direct output of managing program issues.
Per PMI's Standard for Program Management, the Manage Program Issues process produces two outputs: change requests and program issues register updates. The issues register is the primary tracking log for all program issues and must be updated to reflect status changes, resolution actions, and outcomes as issues are managed throughout the program lifecycle.
Concept tested: Manage Program Issues process outputs
Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-program-management