nerdexam
PMIPMI

PGMP · Question #175

PGMP Question #175: Real Exam Question with Answer & Explanation

The correct answer is A: Create an entry in the lessons learned documentation and explain her reasoning behind the. See the full explanation below for the reasoning.

Program Governance

Question

Martha is the program manager for her organization. One of the projects of a program is done but is also considerably over budget. Kay, the project manager, has elected to crash the project in order to recoup schedule delays but this increased the project costs. What should Martha instruct Kay to do with the information regarding the schedule delays and cost overruns?

Options

  • ACreate an entry in the lessons learned documentation and explain her reasoning behind the
  • BFile the information as part of the project final report.
  • CCreate a variance report.
  • DCreate an exceptions report.

Topics

#Lessons Learned#Program Governance#Organizational Process Assets#Program Closure

Community Discussion

No community discussion yet for this question.

Full PGMP PracticeBrowse All PGMP Questions