nerdexam
PMI

PFMP · Question #6

Which of the following are the input of "Optimize Portfolio"? (Choose two.)

The correct answer is B. Portfolio Process Assets D. Portfolio Reports. Portfolio Process Assets and Portfolio Reports are the defined inputs to the Optimize Portfolio process.

Performance Management

Question

Which of the following are the input of "Optimize Portfolio"? (Choose two.)

Options

  • APortfolio Strategic Plan
  • BPortfolio Process Assets
  • CPortfolio Charter
  • DPortfolio Reports

How the community answered

(62 responses)
  • A
    3% (2)
  • B
    89% (55)
  • C
    8% (5)

Why each option

Portfolio Process Assets and Portfolio Reports are the defined inputs to the Optimize Portfolio process.

APortfolio Strategic Plan

The Portfolio Strategic Plan is an input to other portfolio processes but is not a defined direct input to the Optimize Portfolio process.

BPortfolio Process AssetsCorrect

Portfolio Process Assets provide historical information, guidelines, and lessons learned that inform optimization decisions about the portfolio mix.

CPortfolio Charter

The Portfolio Charter authorizes the portfolio at a high level and is not a direct input to the Optimize Portfolio process.

DPortfolio ReportsCorrect

Portfolio Reports supply current performance, status, and risk data needed to evaluate and optimize the portfolio component mix.

Concept tested: Optimize Portfolio process inputs

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Optimization#Portfolio Management Processes#Process Inputs#Portfolio Performance Management

Community Discussion

No community discussion yet for this question.

Full PFMP Practice