PFMP · Question #6
Which of the following are the input of "Optimize Portfolio"? (Choose two.)
The correct answer is B. Portfolio Process Assets D. Portfolio Reports. Portfolio Process Assets and Portfolio Reports are the defined inputs to the Optimize Portfolio process.
Question
Which of the following are the input of "Optimize Portfolio"? (Choose two.)
Options
- APortfolio Strategic Plan
- BPortfolio Process Assets
- CPortfolio Charter
- DPortfolio Reports
How the community answered
(62 responses)- A3% (2)
- B89% (55)
- C8% (5)
Why each option
Portfolio Process Assets and Portfolio Reports are the defined inputs to the Optimize Portfolio process.
The Portfolio Strategic Plan is an input to other portfolio processes but is not a defined direct input to the Optimize Portfolio process.
Portfolio Process Assets provide historical information, guidelines, and lessons learned that inform optimization decisions about the portfolio mix.
The Portfolio Charter authorizes the portfolio at a high level and is not a direct input to the Optimize Portfolio process.
Portfolio Reports supply current performance, status, and risk data needed to evaluate and optimize the portfolio component mix.
Concept tested: Optimize Portfolio process inputs
Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management
Topics
Community Discussion
No community discussion yet for this question.