Portfolio management processes are performed in an environment broader than a portfolio; therefore, an organization-level implementation team supported by executive management, a governing body, and…

The correct answer is D. Communicate the portfolio management implementation plan. After defining roles and responsibilities for portfolio management implementation, the first next step is to communicate the implementation plan so all stakeholders understand expectations before any deployment begins.

Establishing and Implementing Portfolio Management

Question

Portfolio management processes are performed in an environment broader than a portfolio; therefore, an organization-level implementation team supported by executive management, a governing body, and portfolio managers join forces to implement organization-level portfolio management processes. After Defining roles and responsibilities for portfolio management process implementation, what should be the FIRST next step?

Options

  • ADefine and deploy detailed portfolio management processes and provide training to staff and
  • BChanging business processes
  • CDeveloping the Portfolio Strategic Plan
  • DCommunicate the portfolio management implementation plan

How the community answered

(25 responses)
  • A
    16% (4)
  • B
    8% (2)
  • C
    4% (1)
  • D
    72% (18)

Why each option

After defining roles and responsibilities for portfolio management implementation, the first next step is to communicate the implementation plan so all stakeholders understand expectations before any deployment begins.

ADefine and deploy detailed portfolio management processes and provide training to staff and

Deploying detailed processes and providing training is a subsequent step that logically follows after the plan has been communicated and stakeholder alignment has been achieved.

BChanging business processes

Changing business processes is a downstream implementation activity that occurs during or after the rollout phase, not immediately after defining roles.

CDeveloping the Portfolio Strategic Plan

Developing the Portfolio Strategic Plan is an earlier foundational activity that precedes the role definition step referenced in the question.

DCommunicate the portfolio management implementation planCorrect

Communicating the portfolio management implementation plan ensures that all affected stakeholders - including executives, portfolio managers, and staff - understand the defined roles, the upcoming changes, and the timeline. This alignment is a prerequisite to effective deployment of processes and training, as stakeholders who are uninformed cannot support or adopt the new processes.

Concept tested: Sequencing of portfolio management implementation steps

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Management Implementation#Organizational Change Management#Communication Management#Process Implementation

Community Discussion

No community discussion yet for this question.

Full PFMP Practice