Updates to schedules i.e. resource, funding, benefits, are results of Developing the Portfolio Performance Management Plan process. Where should these updates be recorded?
The correct answer is C. Portfolio update. Updates to schedules - including resource schedules, funding schedules, and benefits realization schedules - that result from the Developing the Portfolio Performance Management Plan process are recorded as Portfolio Updates (Option C). The portfolio document itself is updated to
Question
Updates to schedules i.e. resource, funding, benefits, are results of Developing the Portfolio Performance Management Plan process. Where should these updates be recorded?
Options
- APortfolio Management Plan updates
- BEnterprise Environmental Factors Update
- CPortfolio update
How the community answered
(51 responses)- A8% (4)
- B4% (2)
- C88% (45)
Explanation
Updates to schedules - including resource schedules, funding schedules, and benefits realization schedules - that result from the Developing the Portfolio Performance Management Plan process are recorded as Portfolio Updates (Option C). The portfolio document itself is updated to reflect the revised timelines and allocations. Option A (Portfolio Management Plan updates) would apply to changes in the overarching management approach or governance, not schedule-level details. Option B (Enterprise Environmental Factors Update) reflects changes to the broader organizational environment and is not an output for schedule tracking. The portfolio is the living document that captures the current state of all components and their schedules.