Updates to schedules i.e. resource, funding, benefits, are results of Developing the Portfolio Performance Management Plan process. Where should these updates be recorded?
Options
- APortfolio Management Plan updates
- BEnterprise Environmental Factors Update
- CPortfolio update
Topics
#Portfolio Performance Management#Portfolio Updates#Portfolio Information Management#Portfolio Records