PFMP · Question #290

You are managing a large construction portfolio. Recently, and due to budget cuts, you have been having resources issues on multiple initiatives and has been struggling with maintaining a healthy…

The correct answer is A. Finite Capacity planning. Finite Capacity Planning is the practice of scheduling and allocating resources based on their actual, limited (finite) availability – as opposed to infinite capacity planning, which ignores real-world constraints. When you have scarce machinery shared across three major…

Portfolio Resource Management

Question

You are managing a large construction portfolio. Recently, and due to budget cuts, you have been having resources issues on multiple initiatives and has been struggling with maintaining a healthy resource allocations. You are currently analyzing the capability and capacity for scarce machinery resources shared across three major programs in the portfolio. What are you currently applying?

Options

  • AFinite Capacity planning
  • BResource Schedules
  • CResource Management Tools
  • DResource Smoothing

How the community answered

(60 responses)
  • A
    78% (47)
  • B
    3% (2)
  • C
    13% (8)
  • D
    5% (3)

Explanation

Finite Capacity Planning is the practice of scheduling and allocating resources based on their actual, limited (finite) availability – as opposed to infinite capacity planning, which ignores real-world constraints. When you have scarce machinery shared across three major programs and you are analyzing how much of that limited capacity exists and how it should be allocated, you are applying Finite Capacity Planning. This technique ensures that resource demand does not exceed actual supply and helps make realistic, achievable plans. Resource Schedules (B) are an output/artifact, not the analytical technique. Resource Management Tools (C) is a broad category of software/systems. Resource Smoothing (D) is a scheduling technique that adjusts task timing to avoid resource overloads but does not change the project end date – it is a more specific and different concept than finite capacity planning.