Which two options do you consider when creating a pre-processing data transform? (Choose two.)
The correct answer is A. The effect if the flow action is reloaded C. The potential reuse of the flow of the flow action. See the full explanation below for the reasoning.
Question
Which two options do you consider when creating a pre-processing data transform? (Choose two.)
Options
- AThe effect if the flow action is reloaded
- BThe timing of the commit for the flow action
- CThe potential reuse of the flow of the flow action
- DThe security setting for the flow action
How the community answered
(38 responses)- A82% (31)
- B13% (5)
- D5% (2)