Question

A list report includes columns for purchase requests and regional cost centers. A manager wants the report to show the total number of purchase requests for each of the regional cost centers. How would you configure the report definition?

Options

  • AUse the purchase requests column to group the cost centers.
  • BSummarize the regional cost centers by count.
  • CFilter the results so that only cost center and purchase requests are included in the
  • DSummarize the purchase requests column by count.

Unlock PEGACSA72V1 to see the answer