The correct answer is A. longer schedules E. higher risk. See the full explanation below for the reasoning.
Question
When an organization does not use a methodology, orallowsdifferent methodologies on thesame project, the result is usually: (Choose two)
Options
- Alonger schedules
- Blower costs
- Cbigger projects
- Dincreased productivity
- Ehigher risk