PEGACDA71V1 · Question #7
The best situation to use Scrum is when:
The correct answer is C. the team and organization are open to new experiences and fully understand the disciplines associated with. See the full explanation below for the reasoning.
Question
The best situation to use Scrum is when:
Options
- Athe team is coming from a waterfall implementation environment and is willing to try something different
- Bthe project scope is small and there is very little risk to the project schedule
- Cthe team and organization are open to new experiences and fully understand the disciplines associated with
- Dthe team is new to software development but willing to accept a challenging schedule.
How the community answered
(31 responses)- A6% (2)
- B16% (5)
- C74% (23)
- D3% (1)
Community Discussion
No community discussion yet for this question.