Pegasystems
PEGACDA71V1 · Question #20
When allocating resources for an Agile-based project, the project includes six system architects. During the first three sprints, each system architect is allocated 50% to the project, and each is…
The correct answer is C. 1.5 fully allocated system architects. See the full explanation below for the reasoning.
Question
When allocating resources for an Agile-based project, the project includes six system architects. During the first three sprints, each system architect is allocated 50% to the project, and each is estimated to be half as productive as a fully-trained system architect. What is the number of architects you should enter in the Sizing tool for the first three sprints?
Options
- A3 fully allocated system architects.
- B3.5 fully trained system architects.
- C1.5 fully allocated system architects.
- D6 fully allocated system architects.
How the community answered
(36 responses)- A3% (1)
- B8% (3)
- C75% (27)
- D14% (5)
Community Discussion
No community discussion yet for this question.