nerdexam
Pegasystems

PEGACDA71V1 · Question #20

When allocating resources for an Agile-based project, the project includes six system architects. During the first three sprints, each system architect is allocated 50% to the project, and each is…

The correct answer is C. 1.5 fully allocated system architects. See the full explanation below for the reasoning.

Question

When allocating resources for an Agile-based project, the project includes six system architects. During the first three sprints, each system architect is allocated 50% to the project, and each is estimated to be half as productive as a fully-trained system architect. What is the number of architects you should enter in the Sizing tool for the first three sprints?

Options

  • A3 fully allocated system architects.
  • B3.5 fully trained system architects.
  • C1.5 fully allocated system architects.
  • D6 fully allocated system architects.

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    8% (3)
  • C
    75% (27)
  • D
    14% (5)

Community Discussion

No community discussion yet for this question.

Full PEGACDA71V1 Practice