Pegasystems
PEGACDA71V1 · Question #15
Which of the following is themost importantreason to provide acceptance and rejection criteria when detailingaScrum user story?
The correct answer is D. To allow the sprint team to determine if thestory is done at the end of the sprint. See the full explanation below for the reasoning.
Question
Which of the following is themost importantreason to provide acceptance and rejection criteria when detailingaScrum user story?
Options
- ATo differentiate a user story from a use case.
- BTo populate the corresponding required fields on a Specification rule.
- CThe behavior is a best practice.
- DTo allow the sprint team to determine if thestory is done at the end of the sprint.
How the community answered
(32 responses)- A6% (2)
- B13% (4)
- C3% (1)
- D78% (25)
Community Discussion
No community discussion yet for this question.