Select the criteria to use when deciding to use a waterfall methodology. (Choose three.)
The correct answer is A. Requirements are likely already established and unlikely to change during the project. B. The scope of the project is known and unlikely to change during the project. F. Stringent project milestones, or gates, are required by the organization. See the full explanation below for the reasoning.
Question
Select the criteria to use when deciding to use a waterfall methodology. (Choose three.)
Options
- ARequirements are likely already established and unlikely to change during the project.
- BThe scope of the project is known and unlikely to change during the project.
- CRequirements are not well known or may change during the project.
- DThe application is intended for an industry with rapidly changing standards.
- EThere are skilled developers who are adaptable and able to think independently.
- FStringent project milestones, or gates, are required by the organization.
How the community answered
(24 responses)- A75% (18)
- C4% (1)
- D4% (1)
- E17% (4)