PeopleCert
PC0-003 · Question #90
Which of the following is NOT one of MSP's four suggested levels of stakeholder engagement?
The correct answer is C. Formally approve. See the full explanation below for the reasoning.
Question
Which of the following is NOT one of MSP's four suggested levels of stakeholder engagement?
Options
- AMaintain interest
- BActive consultation
- CFormally approve
- DKeep informed
How the community answered
(30 responses)- A7% (2)
- B10% (3)
- C80% (24)
- D3% (1)
Community Discussion