PC0-003 · Question #90

Which of the following is NOT one of MSP's four suggested levels of stakeholder engagement?

The correct answer is C. Formally approve. See the full explanation below for the reasoning.

Question

Which of the following is NOT one of MSP's four suggested levels of stakeholder engagement?

Options

  • AMaintain interest
  • BActive consultation
  • CFormally approve
  • DKeep informed

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    10% (3)
  • C
    80% (24)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.