nerdexam
PeopleCert

PC0-003 · Question #80

Which would you NOT expect to find in a Programme Brief?

The correct answer is D. Roles and responsibilities of programme team members. See the full explanation below for the reasoning.

Question

Which would you NOT expect to find in a Programme Brief?

Options

  • AOutline vision of the future state
  • BCurrent issues and potential risks
  • CClarification of what the programme can achieve
  • DRoles and responsibilities of programme team members

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    11% (3)
  • D
    78% (21)

Community Discussion

No community discussion yet for this question.

Full PC0-003 Practice