Which is a responsibility of the Programme Manager?
The correct answer is D. Reports regularly on programme progress. See the full explanation below for the reasoning.
Question
Which is a responsibility of the Programme Manager?
Options
- AApproves programme's progression to next tranche
- BDefines risk thresholds for the programme's projects
- CEnsures appropriate programme assurance is in place
- DReports regularly on programme progress
How the community answered
(20 responses)- B10% (2)
- C5% (1)
- D85% (17)
Community Discussion
No community discussion yet for this question.