Which is a focus of the Programme Office in managing risks and issues?
The correct answer is D. Maintains the Risk Register and Issue Register. See the full explanation below for the reasoning.
Question
Which is a focus of the Programme Office in managing risks and issues?
Options
- AAccountable for the management and control of all aspects of the risks assigned to them
- BResponsible for the implementation of risk response actions
- CMonitors and reports on business performance issues
- DMaintains the Risk Register and Issue Register
How the community answered
(28 responses)- A7% (2)
- B4% (1)
- C7% (2)
- D82% (23)