PC0-003 · Question #52
PC0-003 Question #52: Real Exam Question with Answer & Explanation
The correct answer is B. Provide a specific focus on transition and operational stability. See the full explanation below for the reasoning.
Question
Why may a Business Change Manager be included within a project board structure of one of the programme's projects?
Options
- AMonitor the project's finances against the costs of the programme
- BProvide a specific focus on transition and operational stability
- CProvide the procedures to manage project risks
- DSupply the project team with an understanding of the complete programme