PC0-003 · Question #52
Why may a Business Change Manager be included within a project board structure of one of the programme's projects?
The correct answer is B. Provide a specific focus on transition and operational stability. See the full explanation below for the reasoning.
Question
Why may a Business Change Manager be included within a project board structure of one of the programme's projects?
Options
- AMonitor the project's finances against the costs of the programme
- BProvide a specific focus on transition and operational stability
- CProvide the procedures to manage project risks
- DSupply the project team with an understanding of the complete programme
How the community answered
(40 responses)- A10% (4)
- B85% (34)
- C3% (1)
- D3% (1)