Which activity includes addressing the disadvantages of `doing nothing' to those stakeholders that object to the programme?

The correct answer is D. Conduct a visioning workshop. See the full explanation below for the reasoning.

Question

Which activity includes addressing the disadvantages of `doing nothing' to those stakeholders that object to the programme?

Options

  • AAnalyse stakeholders
  • BSum ma rise risks
  • CCarry out a health check
  • DConduct a visioning workshop

How the community answered

(69 responses)
  • A
    4% (3)
  • B
    3% (2)
  • C
    12% (8)
  • D
    81% (56)

Community Discussion

No community discussion yet for this question.