PeopleCert
PC0-003 · Question #144
Which of these would you NOT usually find in a Business Case?
The correct answer is A. Overall programme schedule showing the relative sequencing of the projects. See the full explanation below for the reasoning.
Question
Which of these would you NOT usually find in a Business Case?
Options
- AOverall programme schedule showing the relative sequencing of the projects
- BInvestment appraisal
- CEstimated costs and overall timescales
- DCashflow forecast
How the community answered
(40 responses)- A73% (29)
- B15% (6)
- C5% (2)
- D8% (3)
Community Discussion
No community discussion yet for this question.