PeopleCert
PC0-003 · Question #142
Which is ensured by the Business Change Manager in the process Realizing the Benefits?
The correct answer is C. Readiness of the organization to implement the changes. See the full explanation below for the reasoning.
Question
Which is ensured by the Business Change Manager in the process Realizing the Benefits?
Options
- AOptimal running of the programme verified by audits and reviews
- BEffective benefits realization through creating a Benefits Management Strategy
- CReadiness of the organization to implement the changes
- DAlignment of project scope with benefits realization
How the community answered
(37 responses)- A8% (3)
- B3% (1)
- C73% (27)
- D16% (6)
Community Discussion
No community discussion yet for this question.