Which describes the result of a risk on a programme?
The correct answer is D. Risk effect. See the full explanation below for the reasoning.
Question
Which describes the result of a risk on a programme?
Options
- ARisk cause
- BRisk appetite
- CRisk aggregation
- DRisk effect
How the community answered
(18 responses)- A11% (2)
- C6% (1)
- D83% (15)
Community Discussion