What is used to link activities within the service value chain?

The correct answer is C. Opportunity, demand and value. See the full explanation below for the reasoning.

Question

What is used to link activities within the service value chain?

Options

  • AService level agreements
  • BInputs, outputs and triggers
  • COpportunity, demand and value
  • DService desk

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    4% (1)
  • C
    80% (20)
  • D
    4% (1)