What is a change schedule PRIMARILY used for?
The correct answer is D. To help plan changes, assist in communication and avoid conflicts. See the full explanation below for the reasoning.
Question
What is a change schedule PRIMARILY used for?
Options
- ATo help plan, authorize and schedule emergency changes
- BTo publish a list of service requests that users can select
- CTo ensure that a single change authority reviews every change
- DTo help plan changes, assist in communication and avoid conflicts
How the community answered
(41 responses)- A5% (2)
- B5% (2)
- C15% (6)
- D76% (31)