nerdexam
PeopleCert

PC0-001 · Question #686

What happens if a workaround becomes the permanent way of dealing with a problem that cannot be resolved cost-effectively?

The correct answer is B. The problem remains in the known error status. See the full explanation below for the reasoning.

Question

What happens if a workaround becomes the permanent way of dealing with a problem that cannot be resolved cost-effectively?

Options

  • AThe problem record is deleted
  • BThe problem remains in the known error status
  • CA change request is submitted to change control
  • DProblem management restores the service as soon as possible

How the community answered

(19 responses)
  • A
    5% (1)
  • B
    74% (14)
  • C
    16% (3)
  • D
    5% (1)

Community Discussion

No community discussion yet for this question.