Arrange the following steps of software lifecycle in correct order. 1. Retire 2. Test 3. Operate 4. Deploy 5. Ideation 6. Develop 7. Design
The correct answer is A. Ideation, Design, Develop, Deploy, Test, Operate, Retire. See the full explanation below for the reasoning.
Question
Arrange the following steps of software lifecycle in correct order. 1. Retire 2. Test 3. Operate 4. Deploy 5. Ideation 6. Develop 7. Design
Options
- AIdeation, Design, Develop, Deploy, Test, Operate, Retire
- BRetire, Test, Operate, Deploy, Ideation, Develop, Design
- CNone of the above
- DIdeation, Test, Develop, Deploy, Design, Operate, Retire
How the community answered
(39 responses)- A82% (32)
- B5% (2)
- C10% (4)
- D3% (1)