PC0-001 · Question #613

Which is the CORRECT approach for managing a large improvement initiative as smaller iterations?

The correct answer is D. Each iteration should be continually re-evaluated based on feedback. See the full explanation below for the reasoning.

Question

Which is the CORRECT approach for managing a large improvement initiative as smaller iterations?

Options

  • AEach iteration should be designed before starting the initiative and implemented without feedback
  • BFeedback should only be taken into account when one iteration fails to meet its objective
  • CFeedback should be reduced for large improvements as it is unlikely that circumstances will
  • DEach iteration should be continually re-evaluated based on feedback

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    16% (5)
  • D
    74% (23)