Which is NOT a sub-process of capacity management?

The correct answer is A. People capacity management. See the full explanation below for the reasoning.

Question

Which is NOT a sub-process of capacity management?

Options

  • APeople capacity management
  • BComponent capacity management
  • CBusiness capacity management
  • DService capacity management

How the community answered

(21 responses)
  • A
    76% (16)
  • B
    5% (1)
  • C
    10% (2)
  • D
    10% (2)