P_SD_65 · Question #7
A customer uses make-to-order production with assembly processing. How do you schedule a sales order when components are already produced and procured?
The correct answer is A. Create a production order directly from the sales order. See the full explanation below for the reasoning.
Question
A customer uses make-to-order production with assembly processing. How do you schedule a sales order when components are already produced and procured?
Options
- ACreate a production order directly from the sales order.
- BUse a planning run to generate a planning order for the sales order.
- CExplode the bill of material and plan dependent demands for the sales order.
- DUse heuristic planning for material reservation of the sales order.
How the community answered
(64 responses)- A80% (51)
- B11% (7)
- C3% (2)
- D6% (4)