A customer uses make-to-order production with assembly processing. How do you schedule a sales order when components are already produced and procured?

The correct answer is A. Create a production order directly from the sales order. See the full explanation below for the reasoning.

Question

A customer uses make-to-order production with assembly processing. How do you schedule a sales order when components are already produced and procured?

Options

  • ACreate a production order directly from the sales order.
  • BUse a planning run to generate a planning order for the sales order.
  • CExplode the bill of material and plan dependent demands for the sales order.
  • DUse heuristic planning for material reservation of the sales order.

How the community answered

(64 responses)
  • A
    80% (51)
  • B
    11% (7)
  • C
    3% (2)
  • D
    6% (4)