Your customer is planning to replace the current Excel based capacity planning with an SAP based ATP solution. How do you prevent overbooking of the plant?
Options
- AImplement an ATP check against product allocations which are designed as production capacity.
- BImplement an ATP check against replenishment lead time.
- CImplement a multi-level ATP check against component availability in PP.
- DImplement a rescheduling with ATP check.