Question
Your customer is using ATP check including replenishment lead time which is not maintained in material master. Which time indicators are used in this case?
Options
- AIn-house production: goods receipt processing time + pick/pack time
- BExternal procurement: purchasing department processing time + planned delivery time
- CIn-house production: in-house production time + pick/pack time
- DExternal procurement: planned delivery time + loading time