The customer wants to implement an inter-company process. Which changes are required? (Choose three)
The correct answer is A. Create a new condition record for the delivering sales organization. B. Extend the material master with the delivering sales organization and delivery plant. C. Assign the ship-to-party to the delivering sales organization. See the full explanation below for the reasoning.
Question
The customer wants to implement an inter-company process. Which changes are required? (Choose three)
Options
- ACreate a new condition record for the delivering sales organization.
- BExtend the material master with the delivering sales organization and delivery plant.
- CAssign the ship-to-party to the delivering sales organization.
- DAssign the sold-to-party to the delivering sales organization.
- ECreate new scheduling agreements in the delivering sales organization.
How the community answered
(31 responses)- A84% (26)
- D10% (3)
- E6% (2)