SAP
P_SD_65 · Question #10
Since release 4.5A, you can valuate the materials for the sales order together with the materials for the make-to-stock inventory. Prerequisite is that the costs have been collected on a specific…
The correct answer is D. Production Order. See the full explanation below for the reasoning.
Question
Since release 4.5A, you can valuate the materials for the sales order together with the materials for the make-to-stock inventory. Prerequisite is that the costs have been collected on a specific order. Which one?
Options
- ASales Order
- BPlanned Order
- CPurchase Order
- DProduction Order
How the community answered
(21 responses)- A5% (1)
- B14% (3)
- C5% (1)
- D76% (16)
Community Discussion