What are risk identification and risk assessment workshops typically used for?

The correct answer is B. Identify threats as part of project initiation. See the full explanation below for the reasoning.

Question

What are risk identification and risk assessment workshops typically used for?

Options

  • ADefine the relative priority of each investment objective
  • BIdentify threats as part of project initiation
  • CBrainstorm objectives for a project
  • DDefine measures in a Benefit Profile

How the community answered

(28 responses)
  • A
    7% (2)
  • B
    71% (20)
  • C
    14% (4)
  • D
    7% (2)