Which occurs when the P3O implementation programme is closed?
The correct answer is D. P3O capability becomes business as usual. See the full explanation below for the reasoning.
Question
Which occurs when the P3O implementation programme is closed?
Options
- AVision Statement is refined to reflect delivery
- BBlueprint is produced to document processes
- CRisks to the implementation are captured
- DP3O capability becomes business as usual