P3OF · Question #73
Which of the following are key stakeholders in a temporary Project Office? 1. Organization Portfolio Office 2. Business as usual staff 3. Suppliers to the project 4. Project Board members
The correct answer is C. 1, 3, 4. See the full explanation below for the reasoning.
Question
Which of the following are key stakeholders in a temporary Project Office? 1. Organization Portfolio Office 2. Business as usual staff 3. Suppliers to the project 4. Project Board members
Options
- A1, 2, 3
- B1, 2, 4
- C1, 3, 4
- D2, 3, 4
How the community answered
(58 responses)- A14% (8)
- B3% (2)
- C76% (44)
- D7% (4)