Which of the following are key stakeholders in a temporary Project Office? 1. Organization Portfolio Office 2. Business as usual staff 3. Suppliers to the project 4. Project Board members

The correct answer is C. 1, 3, 4. See the full explanation below for the reasoning.

Question

Which of the following are key stakeholders in a temporary Project Office? 1. Organization Portfolio Office 2. Business as usual staff 3. Suppliers to the project 4. Project Board members

Options

  • A1, 2, 3
  • B1, 2, 4
  • C1, 3, 4
  • D2, 3, 4

How the community answered