P3OF · Question #61
Which should be documented in a Blueprint?
The correct answer is C. Need for Business Cases for mission-critical programmes to be reported to the Portfolio Board. See the full explanation below for the reasoning.
Question
Which should be documented in a Blueprint?
Options
- ABenefit Profiles for individual benefits to be delivered by the P3O
- BTransition plans for the implementation of business change into business as usual
- CNeed for Business Cases for mission-critical programmes to be reported to the Portfolio Board
- DActual Highlight Reports issued by individual projects
How the community answered
(57 responses)- A4% (2)
- B12% (7)
- C77% (44)
- D7% (4)