EXIN
P3OF · Question #6
Which is NOT an independent assurance service provided by a P3O to a project?
The correct answer is D. Providing project support to a Project Manager. See the full explanation below for the reasoning.
Question
Which is NOT an independent assurance service provided by a P3O to a project?
Options
- ACo-ordinating gated reviews
- BFacilitating lessons reviews
- CFacilitating regular health checks
- DProviding project support to a Project Manager
How the community answered
(31 responses)- A6% (2)
- B3% (1)
- C10% (3)
- D81% (25)
Community Discussion
No community discussion yet for this question.