P3OF · Question #6

Which is NOT an independent assurance service provided by a P3O to a project?

The correct answer is D. Providing project support to a Project Manager. See the full explanation below for the reasoning.

Question

Which is NOT an independent assurance service provided by a P3O to a project?

Options

  • ACo-ordinating gated reviews
  • BFacilitating lessons reviews
  • CFacilitating regular health checks
  • DProviding project support to a Project Manager

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    10% (3)
  • D
    81% (25)